Road, watermain and bridge work across the ward, from this fall's construction to what's planned for the next few years.
Under construction

Foch Avenue, Lloyd George Avenue and Dover Drive
New watermains and water services on Foch Avenue, from Jellicoe Avenue to Edgeware Drive, are done. Crews came back on October 19 to resurface Foch and Lloyd George, and to rebuild Dover Drive between Lloyd George and Brown's Line with a new sidewalk. Work is scheduled through December 2026.
Work area. Map: City of Toronto.

Queen Elizabeth Boulevard: new watermain, sewer and sidewalks
Crews are replacing the watermain and sanitary sewer on Queen Elizabeth Boulevard from Canmotor Avenue to Royal York Road, then repaving the road. New sidewalks are going in where there are none today, from 10 Queen Elizabeth Street to Taymall Avenue and from Plastics Avenue to Canmotor Avenue. Expect one lane of traffic during the work, which the City expects to finish in spring 2027.

Toffee Court: new sewer, watermain and road
After a delay this summer, work started this fall to replace the storm sewer and watermain on Toffee Court, off New Toronto Street, and then repave the road.

Glenellen, Kirk Bradden, Sunnylea and Kingslea resurfacing
Sections of Glenellen Drive West, Kirk Bradden Road West, Sunnylea Avenue West and Kingslea Drive are being resurfaced, with 150 metres of new watermain on Kingslea. Work runs from mid-October to December 2026, and the City will post street-by-street updates.
Work limits. Map: City of Toronto.

Queensway bridge over the Humber River
The City has been repairing The Queensway bridge over the Humber since July so it stays safe for drivers and people walking. The work was scheduled to wrap up this month.

Gardiner Expressway Section 3: bridge repairs
Crews are repairing five bridges: the Park Lawn Road and Mimico Creek overpasses, the westbound Park Lawn on-ramp, and the bridges that carry Kipling and Islington over the Gardiner. The Park Lawn westbound on-ramp is scheduled to stay closed through December 2026. Full rehabilitation from Highway 427 to the Humber River could start as soon as 2027.
Bridge locations. Map: City of Toronto.
Other City work this year
These streets have 2026 construction notices from the City. The City's Ward 3 page has each notice and who to contact.
| Street | Work | Notice |
|---|---|---|
| Alcan AvenueBrown's Line to Enfield Avenue | Road resurfacing | August 2026 |
| Boncer Drive | Road resurfacing | August 2026 |
| Forty First StreetLake Shore Boulevard West to Lake Promenade | Watermain work | July 2026 |
| Staffordshire Place | New watermain and resurfacing | July 2026 |
| Gardenvale Road, Eagle Road and Van Dusen Boulevard | Road resurfacing | September 2026 |
| Stanley Avenue | Road resurfacing | September 2026 |
| Jopling Avenue SouthBloor Street West to Dundas Street West | Watermain cleaning and relining | June 2026 |
| Manstor Road and North Queen Street | Watermain cleaning and relining | March 2026 |
| Eastside Drive | Road resurfacing | March 2026 |
| Fourth StreetLake Shore Boulevard West to the south end | Road resurfacing | March 2026 |
Planned

Old Mill Road bridge repairs
The bridge over the pedestrian crossing is getting deck repairs, waterproofing and a new road surface. Old Mill Road will be closed at the bridge from November 16 to December 11. Work underneath continues without a road closure until March 2027.
Bridge location and walking route. Map: City of Toronto.

The Queensway Complete Street
Council approved this in 2022. The City will rebuild The Queensway from the Humber River to Burma Drive with a new watermain, raised cycle tracks, wider sidewalks and a centre median between Stephen Drive and Park Lawn Road. The City's construction map shows the work in 2027 and 2028.
Artist rendering of The Queensway Complete Street. Image: City of Toronto.

Alderwood basement flooding protection
To cut the risk of basement flooding, the City plans to upgrade sewers on streets across Alderwood, including Westhead, Savona, Rufford, Dunning, Burlingame, Roseland and Woodbury. Albright Avenue will be rebuilt with a new sidewalk, and Horner Avenue gets a new watermain from Burlingame to Delma. The City's construction map shows this from spring 2027 to 2031.
Basement flooding protection program. Image: City of Toronto.

Alderwood watermain renewal
The City plans to renew older watermains in 2027 on Valermo, Sheldon, Rimilton, Delta, Gamma, Bellman, Connorvale, Robindale and Paula.
Horner Avenue and Beta Street, Alderwood. Photo: Wikimedia Commons.

Islington Avenue, Kipling Avenue and Belvedere Boulevard
The City started design work in spring 2026 on infrastructure upgrades for these streets. Its construction map shows new watermains in 2027 on Islington from The Queensway to Athol Avenue, and on Kipling from Burnhamthorpe Road to Bloor Street.

Westside Drive and North Queen Street
The City is preparing to remove a culvert on North Queen Street near The East Mall. Westside Drive, off The West Mall, is set to be rebuilt in 2027 and 2028 with a new sidewalk and safety upgrades.

Legion Road extension
A new street connecting Legion Road under the rail line, between Lake Shore Boulevard West and the Gardiner/Park Lawn off-ramp. It will have one lane each way plus walking and cycling connections, to ease congestion at Park Lawn and Lake Shore. Detailed design is starting, with public consultation expected in 2027.
Legion Road North. Photo: City of Toronto.