Playgrounds, park upgrades and free things to do near you.
Done

Miles Road End Parkette
Finished in November 2026: a new pathway into the parkette, benches facing the lake and an accessible chess table.
Miles Road shoreline. Photo: TRCA.

Grand Avenue Park
Grand Avenue Park reopened in November 2025 with a new accessible playground, finishing Phase 2. Part of the playground is briefly closed for safety fixes; the rest of the park is open. The next phase, a washroom building and community hub, is scheduled from fall 2026 to spring 2028.
Planned washroom pavilion. Rendering: City of Toronto.

Park Lawn Park playground
The new playground is open. Lighting work in the park runs from October to December 2026.
The new playground. Photo: City of Toronto.

Alderwood Memorial Park playground
The playground at 215 Sheldon Avenue was rebuilt with new equipment in 2024 through the City's Playground Enhancement Program.
The new playground. Photo: City of Toronto.

Delma Park playground
The playground at 38 Delma Drive was rebuilt with new equipment in 2024 through the City's Playground Enhancement Program.
The new playground. Photo: City of Toronto.

Hillside Park playground
The playground at 185 Hillside Avenue was rebuilt with new equipment in 2025 through the City's Playground Enhancement Program.
The new playground. Photo: City of Toronto.

Lambton-Kingsway Park playground
The playground at 37 Marquis Avenue was rebuilt with new equipment in 2025 through the City's Playground Enhancement Program.
The new playground. Photo: City of Toronto.

Humber Bay Park East pond and wetland
The park reopened in July 2026 with a renewed pond, wetland and walkways. Final planting and park furniture are going in this fall. The City and TRCA are also looking at ways to improve water flow in the pond, to cut down on heavy plant growth in the summer. Two new park buildings, one for recreation and one for park operations, are planned next, with construction expected from 2027 to 2030.
New boardwalk. Photo: City of Toronto.

Birmingham Street Parkette
Opened June 21, 2025 at 265 Twelfth Street, with fitness equipment, games tables, shaded seating, paths and new planting.
Shaded games tables. Photo: City of Toronto.
Under construction

Cinema Park, 1023 The Queensway
Construction started in summer 2026 on Cinema Park, a new 1,850 m² City park with a multi-use plaza, playground, seating and public art. It is expected to open in early 2027. It is separate from the redevelopment at 1025 The Queensway.
Park design. Image: City of Toronto.

Amos Waites Park outdoor pool
The pool at Amos Waites Park, 2441 Lake Shore Boulevard West, is getting a new accessible pool basin, plus upgrades to the deck, fence and change rooms. Construction started in September 2026 and is expected to finish in fall 2027. The splash pad and outdoor washroom closed early for the season because of the work.
Amos Waites Park outdoor pool.


New entrance to Colonel Samuel Smith Park
A new paved entrance to Colonel Samuel Smith Park is going in at Thirteenth Street and Morrison Street, with seating, P-gates and new planting. The City’s schedule has construction starting in summer 2026 and finishing this fall. The informal path there is closed while crews work.
Colonel Samuel Smith Park shoreline. Photo: TRCA.
The City’s project sign at Thirteenth Street.
Planned

Sand Beach Road Parkette expansion
The parkette is growing east toward Lake Shore. The City bought 2707 Lake Shore Boulevard West in May 2026 and 1 Sand Beach Road in August 2026, and 1A Sand Beach Road will be transferred to Parks later. That means more waterfront park space and a direct path from Lake Shore. Public consultation and design are expected to start in 2027.
I'll keep pushing to make sure the bigger park is fully funded.
Expansion lands and when the City bought them.

Six Points Park expansion and Dunkip Park
An expanded Six Points Park and a new Dunkip Park, with gathering spaces, planting and Indigenous placekeeping. Construction is scheduled from spring to fall 2027. Dates for Etobicoke City Centre Park and the Linear Park haven't been set.
Park district plan. Image: City of Toronto.

New parks near Portland Street and Audley Street
Two new parks are coming at the northeast and northwest corners of Audley Street and Newcastle Street, delivered through nearby developments. The City collected ideas from residents in late 2025, and design options are next. Construction is expected to start in spring 2029.
Location of the new parks. Map: City of Toronto.

Thirty-Eighth Street playground
The City is hiring a builder this fall, will rebuild the playground in spring 2027, and plans to reopen it in summer 2027.
Thirty-Eighth Street Park today. Photo: City of Toronto.

Park Lawn Park basketball court
A new basketball court is coming to Park Lawn Park, between the baseball diamond and the sports field, with construction set for spring 2027. Residents asked for it, and my office worked with City staff to get it planned.
Proposed court location. Photo: City of Toronto.
More parks in the planning stage
Work at King’s Mill Park, Tom Riley Park and Mimico Arena is in the planning stage.
Islington to Royal York hydro corridor: staff reported on a possible park and trail in the corridor in September 2025. The next step is Hydro One’s review of the concept plan. If Hydro One approves it in principle, staff will request funding in a future City budget and then begin community discussions. Community Council item EY25.10
Have an idea for a park near you? Email my office at [email protected].
Services

Borrow sports equipment at Ourland Park
Borrow basketballs, soccer balls and more for free at 18 Ourland Avenue. The City page explains how to borrow with the app or at a recreation centre.
A Play for Free equipment box.
On hold

Syd Cole Park expansion
The expansion is tied to the townhouse development at 3526 Lake Shore Boulevard West. That development is on hold, so the park work is paused too.
Expansion design, 2024. Image: City of Toronto.
New parks near Dundas Street West and Thomas Riley Road
Two new parks, southeast of Shorncliffe Road and Dundas Street West near Cloverdale Park, are tied to the development at 5415 Dundas Street West. The developer has paused that project, so the parks are paused too.

Spring Garden Park playground
The playground project is on hold after residents asked to keep the park's natural setting. The City is working with my office on next steps.